August 2009 Restoration Update

Posted by Joel on Saturday, September 12
Filed under: Lighthouse News, Restoration Updates

The following items have been completed or nearly completed during the month of August 2009:

Washing of the interior walls to get rid of all the dust from sanding has begun

Staining and varnishing of the 2nd floor bedroom floors has started.

The outside railings have been installed most of the way around the new base.  The remaining pieces are being fabricated and will be installed next month.

Prep work on the base has begun to allow the docks to be attached once they are complete.

The remaining outside walls that were not painted in the fall of 2008 have been finished.  The window trim will be done next month.

Upcoming jobs:

Paint the tin roof and stain the mansard shingles.

Thank you for your continued support