July 2009 Restoration Update
Posted on Friday, August 14
Filed under: Lighthouse News, Restoration Updates
The following items have been completed or nearly completed during the month of July 2009:
The scraping of the upstairs bedrooms of old floor covering in preparation of new varnish has been completed. All grout between the boards has also been removed.
The spindles for the stairs leading to the second floor have been stripped and have been primed and stained.
The docks are almost complete and will be taken out to the lighthouse in September.
The NW outside wall, with the exception of the windows, has been scraped, primed, and one finish coat applied. The NE outside wall has been scraped, and primed. The SW outside wall has had an addition finish coat over most of it.
Upcoming jobs:
Paint the remaining outside walls that were not painted in the fall of 2008 and during June 2009
Paint the tin roof and stain the mansard shingles.
Thank you for your continued support