May 2009 Restoration Update
Posted by Joel on Sunday, June 21
Filed under: Lighthouse News, Restoration Updates
The following items have been completed or nearly completed during the month of May 2009:
Work has started on scraping the upstairs bedrooms of old floor covering in preparation of new varnish.
The kitchen was updated by the DIY network for their new series Operation Salvage. You can find out when this will be on by checking the DIY web site.
The Estuary Steward was put in the water and work to get it running has started.
The docks have been taken to a workshop in Newburgh to be assembled and then put in the water to be attached to the light house later this summer.
The following items are still “in progress” and on-going:
Various windows are being repaired
Continuation of preparing the upstairs floors for varnishing
Upcoming jobs:
Paint the 2 remaining outside walls that were not painted in the fall of 2008
Paint the tin roof and stain the mansard shingles.
Thank you for your continued support