July 2008 Restoration Update

Posted on Wednesday, August 20
Filed under: Lighthouse News, Restoration Updates

The following items have been completed or nearly completed during the month of July 2008:

The concrete rim has been poured and looks great (see pictures below)
Wooden steps are in place for the kitchen.
The watch room floor and stairs have now been scraped and varnished (see pictures below)
The bathroom is mostly finished except for the plumbing and the toilet solution.
The bathroom wainscoting is complete.
The bathtub needs to be brought down from Certified Marine before the banister goes back up on the staircase.

The following items are still “in progress” and on-going:

The bedroom floors still need work, scraping and sanding before they are varnished
There is still some trim painting to do.
Sanding, priming, painting of various windows is still an on-going job

Upcoming jobs:

Painting – The Ulster County Sheriff work release program will be painting the outside of the lighthouse at the end of August.  It will be completely stripped, then sealed and hand painted (not sprayed on).  We are looking for the LOAN of scaffolding to allow us to reach the upper half of the lighthouse.

The following is a slide show of the granite base work being done

The following is a slide show of the watch room floor and stairs with a fresh coat of varnish on them.